Capacity & Commissioning Targets
In the Mar'26 Qtr, management initiated current financial year targets to commission 1.5 GW of generation and approximately 10 GWh of battery energy storage systems (BESS), allocating 8.5 GWh to merchant operations and 1.5 GWh to FDRE. This builds on an accelerated execution strategy where the Sep'25 Qtr originally guided 1 GWh of merchant BESS for the Mar'26 Qtr, which was upgraded in the Dec'25 Qtr to 2 GWh for Mar'26 and 2 GWh for the Jun'26 Qtr. Forward timelines now specify Neemach charging by Jun'26, NTPC solar by Dec'26, full SJVN FDRE by Mar'27, and the entire 12 GWh under-construction battery portfolio by Mar'28. [Status: Initiated]