Ansal Housing Penalized ₹2.08 Lakh by HRERA for Project Extension Delay

Ansal Housing Limited received an order dated 22nd Oct'26 from the Haryana Real Estate Regulatory Authority (HRERA) imposing a penalty of ₹2,07,867

Ansal Housing Penalized ₹2.08 Lakh by HRERA for Project Extension Delay

Ansal Housing Ltd · Others (Uncategorized) · 23 Oct 2026, 8:28 pm

Ansal Housing Penalized ₹2.08 Lakh by HRERA for Project Extension Delay Ansal Housing Limited received an order dated 22nd Oct'26 from the Haryana Real Estate Regulatory Authority (HRERA) imposing a penalty of ₹2,07,867. The penalty was levied due to a 15-month delay in paying the extension fee for its project, "Ansal Town Yamunanagar DDJAY-SCH-1," calculated at 10% per month on the ₹1,38,578 fee. The company confirmed the financial liability is limited to the penalty amount, with no material impact on its overall financials or operations.