Clean Science and Technology Ltd (CLEAN) Q2FY27 Management Mirror - Sep-2026 Qtr
Performance Chemical II Commissioning Deferred to Jan'27 or Feb'27 From Nov'26/Dec'26 Guided in Jun'26 Qtr
In the Sep'26 Qtr concall, management updated that the Performance Chemical II (ATBS) project is scheduled for commercialization between Q3 FY27 and Q4 FY27, targeting commercial production in Jan'27 or Feb'27. This defers the timeline from the Mar'26 Qtr initial guidance of Sep'26, which had been previously delayed in the Jun'26 Qtr to Nov'26 or Dec'26 Qtr due to labor issues. For periods beyond Sep'26 Qtr, management expects a 20% to 25% capacity utilization in the first calendar year of operations, noting that customer validation, sampling, and stabilization remain key initial milestones.