Capacity Expansion & Operations
Management continues to target the commissioning of its 6 GW integrated facility by Mar'27, with the module line expected by Dec'26, aiming for total installed capacities of 16.3 GW for modules and 8.9 GW for cells by Mar'27. Backward integration plans for ingots and wafers experienced sequential timeline revisions; initially aligned to a Jun'28 timeline in the Sep'25 Qtr, management temporarily withheld formal timelines in the Dec'25 Qtr pending regulatory clarity, before officially outlining a phased 9 GW expansion in the Mar'26 Qtr featuring Phase 1 (5 GW) completion by Mar'29. [Status: Reaffirmed]