Godavari Biorefineries Ltd (GODAVARIB) Q4FY26 Management Mirror - Mar-2026 Qtr
Ethanol Capacity Expansion
Management pushed the commissioning trials for the 200 KLPD grain-based distillery to Jun'26, which is expected to add approximately 60 million liters of annual capacity. The timeline was originally set for the Mar'26 Qtr in the Sep'25 Qtr, but was flagged as delayed due to late equipment receipt in the Dec'25 Qtr before being formally pushed to Jun'26 in the Mar'26 Qtr. [Status: Downgraded]