GREENPOWER Q4 FY26 Guidance vs Delivery (GREENPOWER Management Mirror)

Did GREENPOWER's management deliver what it guided? Guidance vs actual performance and tone changes across recent earnings calls, as of the Q4 FY26 (Mar-2026 Qtr) concall.

Orient Green Power Company Ltd (GREENPOWER) Q4FY26 Management Mirror - Mar-2026 Qtr

Solar Capacity Expansion

The timeline for the 18 MW solar project was pulled forward and then refined across quarters. In the Sep'25 Qtr, the project was slated for completion before Jun'26. In the Dec'25 Qtr, management accelerated the target to before May'26. In the Mar'26 Qtr, guidance was refined to specifically cite a 17.6 MW project commissioning in the Jun'26 Qtr with full production by the Sep'26 Qtr, expected to generate ~INR 14.5 crores in full-year revenue and INR 12.8 crores in EBITDA. [Status: Upgraded]