Expansion & Capex
Management targets commissioning the second colour coating line (increasing capacity to 2,36,000 MT; INR 65 crores outlay) and a 7 MW captive solar plant (INR 30 crores outlay) by Jul'26, reflecting a slight delay from the Jun'26 target set in the Dec'25 Qtr, which itself refined the early Mar'27 timeline cited in the Sep'25 Qtr; meanwhile, plans for a backward-integrated cold rolling mill by Mar'28 remain unchanged since the Sep'25 Qtr blueprint phase. [Status: Downgraded]