NHPC Ltd (NHPC) Q4FY26 Management Mirror - Mar-2026 Qtr
Subansiri Lower Project
In the Mar'25 Qtr, completion of all units was expected by May'26 at an estimated cost of Rs 26,076 Crore; this was revised in the Dec'25 Qtr to Dec'26 at Rs 28,000 Crore, and further delayed in the Mar'26 Qtr to Mar'27 with total project costs escalating to Rs 30,072 Crore. [Status: Downgraded]