Premier Energies Ltd (PREMIERENE) Q4FY26 Management Mirror - Mar-2026 Qtr
Capacity Expansion & Efficiency
The 5.6 GW module plant at Sitarampur is complete, with full production ramp-up expected by May'26, while total cell capacity will shortly reach 10.6 GW. Management reaffirmed that TOPCon cell efficiency, currently at 25.5%, is targeted to hit 25.8% within two quarters, a target upgraded in the Dec'25 Qtr from the initial Sep'25 Qtr goal of 25.2% to 25.4%. The new 7 GW cell line, expanded from an initial 4.8 GW plan in the Sep'25 Qtr, is on track with stabilization expected 4 to 6 months post-commissioning. [Status: Reaffirmed]